Mine seismicity and rockburst risk management – phase II
Project Overview
Project Number
M0355
Total Grant Value
$777,000
Program Area
Project Theme
Engineering in Highly Stressed and Complex Rock Masses
Project Period
2003 - 2006
Summary
Further developing methods and outcomes from M0328, this project had three objectives: maximize the use of seismic monitoring for understanding mine seismicity, develop a quasi-real-time seismic hazard map, and perform seismic risk analyses. By the end of the project the software developed was in use at 15 mines in Australia and Canada.
Seismic hazard was shown to correlate strongly to faults, mining width and rock compressive strength, among other factors.
Keywords: mine seismicity, mine safety, seismic risk, mine seismic monitoring, rockburst risk
Similar Projects